PublishedAugust 1, 2023
NECEC corridor work restarting at Lewiston converter station
Work on the Lewiston converter station, considered a major piece of the project, is expected to resume Thursday.
-
PublishedMay 16, 2023
Work on NECEC transmission line may begin again soon
The Department of Environmental Protection has lifted a stop-work order on the stalled power line project, which is backed by Central Maine Power affiliates.
-
PublishedApril 20, 2023
Powerline verdict to bring significant tax relief to Lewiston
Property tax revenue from CMP's converter station project is projected at $7 million a year, allowing the city to lower its tax rate.
-
PublishedApril 20, 2023
Work can resume on CMP power-line project, jury rules
Construction of the 145-mile line through western Maine has been stalled since a 2021 voter referendum that opposed the $1 billion project.
-
PublishedApril 19, 2023
Future of CMP power line corridor now rests in jury’s hands
Closing arguments in a civil trial focused on whether developers of the stalled 145-mile line sped up construction simply to gain legal rights to continue building.
-
PublishedApril 18, 2023
Defense rests on day 6 of trial over fate of CMP corridor
Jurors heard more conflicting accounts of why construction work sped up on the electricity line, which is supported by Central Maine Power and would extend 145 miles through western parts of the state.
-
PublishedApril 13, 2023
On day 4 of CMP corridor trial, jurors hear details of project timing
A civil trial could determine the fate of the stalled New England Clean Energy Connect power line project, and Thursday's testimony focused on tasks such as clearing trees and installing poles.
-
PublishedApril 12, 2023
On third day, CMP corridor trial zeroes in on construction timing
The fate of the New England Clean Energy Connect project could hinge on when work began along the 145-mile corridor through western Maine – and why.
-
PublishedApril 11, 2023
Power line construction moved ahead on good-faith schedule, jurors told
New England Clean Energy Connect, backed by Central Maine Power and its affiliates, was repeatedly forced to change timeframes, lawyers for the project said on the second day of a civil trial.
-
PublishedApril 10, 2023
Long-awaited trial over future of CMP electricity corridor gets underway
Five years in the making, the trial that could determine the fate of the 145-mile electricity transmission corridor is expected to last 7 days in state Business and Consumer Court.
- 1
- 2
- 3
- …
- 9